CERC Liberalises Grid Access to Green Projects

Central Electricity Regulatory Commission (CERC) has taken an important regulatory initiative. While the threshold capacity for connecting to inter-State grid will be 250 MW for thermal power stations, the threshold has been reduced to 50 MW for the hydro electric generating stations and other generating stations using renewable sources of energy.

Another important regulatory change has been made to permit connectivity to inter-State grid to stations which have individually installed capacity of less than 50 MW but approach the Central Transmission Utility (POWERGRID) collectively with an aggregate installed capacity of 50 MW and above.

State Transmission Utilities in many stations, particularly in North-eastern states, are not presently in a position to extend connectively to their systems and this difficulty was hindering the development of hydro electric stations and renewable source based stations.